Which of the following is not true about bottom-up estimating?
A) The WBS must be accurate and complete before this process can be used.
B) Since the cost is largely independent of the desired accuracy it is the methodology of choice.
C) Its accuracy increases if the activities are smaller.
D) It is not a useful methodology in the early project planning phase.
Answer:
B) Since the cost is largely independent of the desired accuracy it is the methodology of choice.